Break product and engineering goals into GitHub phases, tasks, acceptance criteria, risks, and dependencies.
Decomposes a product or engineering goal into executable GitHub phases, features, tasks, subtasks, acceptance criteria, risks, and native issue dependencies. Use when a project or issue is in PLANNING.

BEFORE YOU INSTALL

Understand the trade-offs.

SECURITY REVIEW

Not yet assessed

Review the original instructions and requested permissions before installing.

No security review is available for this catalog entry yet.

SKILL QUALITY

Not yet assessed

How clearly the skill guides your agent, how complete its workflow is, and how you can check the outcome.

No quality assessment is available for this catalog entry yet.

The full skill.

Original instructions from the publisher’s SKILL.md

# Planning Projects

Transform a goal/specification into an executable work graph.

For a new project from natural language, use `.ai-team/bin/bootstrap-project
--brief FILE` (or `--brief -` for stdin). It creates/reuses the Project and publishes
the validated graph. Its dedicated prompt defines bounded JSON output. Planning
has no GitHub write authority; the deterministic publisher creates issues/edges.
Root/phase/feature/grouping issues stay BACKLOG and are never implementation work.
Only task/subtask leaves with acceptance and validation can become READY. All
leaves stay BLOCKED until the complete graph has been verified; the root's final
completion marker is mandatory before any descendant can run.
Do not regenerate a bootstrap plan on retry: recover it from the tracking issue.

Principles:
- plan outcomes, not fake busywork
- prefer one coherent reviewable outcome per task
- use subtasks only when they improve ownership/dependency/review clarity
- every executable task needs acceptance criteria
- dependencies must be native GitHub relationships where practical
- separate product decisions from implementation
- identify critical path and risks

Each phase needs objective, entry criteria, exit criteria, risks, features/tasks.

Each task needs Goal, Context, In/Out of Scope, Acceptance Criteria, Dependencies, Constraints, Validation, Evidence Required and Risk.

Good tasks are usually one PR, independently reviewable, bounded, and completable by one agent session. Avoid both giant multi-outcome tasks and meaningless microtasks.

Mark only genuinely executable dependency-free tasks READY; blocked work remains BLOCKED.